Alberta Technology Minister Nate Glubish was heckled, booed, and pelted with profanity at the province’s second town hall on artificial intelligence data centres, held Thursday in Redwater, nearby where Meta as started the construction of a $13-billion facility powered by a $4.6-billion natural gas plant. The government insists its strategy protects local water, land, and electricity—but critics say trust has already collapsed after residents were left in the dark for more than two years while the plan took shape.

The hostile reception marked the second straight public meeting to erupt over the province’s data centre ambitions, a sign that community resistance is hardening as major projects move from announcement toward construction. The Redwater event, held in Sturgeon County north of Edmonton, came a month after Meta announced its plans for the region and started construction the same month, and residents lined up at the microphone to demand specifics on safeguards for local resources. Attendees hurled expletives and heckled the minister throughout the night as he fielded questions, according to The Canadian Press.

One woman told Glubish that Premier Danielle Smith’s United Conservative government spent more than two years crafting its strategy and only recently informed nearby residents. “If no one wants this, why are you pushing forward with this?” she asked, drawing applause from much of the room, though event moderator and political staffer Vitor Marciano noted that many in the crowd were not clapping. Other speakers worried the megaproject could drain local water, land and electricity, and some questioned the promised jobs.

Glubish, interrupted repeatedly as he spoke, defended the project’s siting. “This was zoned for this for over 30 years, and now it is coming to fruition,” he said. The minister maintained the province has carefully designed its strategy to protect water supplies, electricity bills and land use, and argued the Meta project carries indirect economic benefits, saying he would choose its 300 jobs over none. He also took heat over the Smith government’s use of the notwithstanding clause.

The dispute over who gains and who pays reflects a larger policy question about artificial intelligence, Taylor Jackson, writing in The Hub, argued. “The question for policymakers—and for workers—isn’t whether AI will matter, but how it will matter for different parts of the Canadian economy, who will benefit the most, and who may lose.”

The gap between short-term and permanent employment is significant. The Sturgeon County facility is expected to employ about 3,000 construction workers at its peak but support just over 300 operational jobs. Meta has said the plant will use a closed-loop liquid-cooling system with dry cooling that eliminates operational water use, and argued such commitments should be written into approvals and verified once facilities are running.

Jackson also observed that governments need a clearer picture of AI’s labour-market consequences before the infrastructure scales up. “We need to understand how AI could impact labour markets to ensure that support systems are prepared to aid in labour transitions, while still reaping the economic gains from the adoption of new technologies,” he wrote.

The resource concerns voiced in Redwater mirror pressures documented across the province, where the government has pitched Alberta as a destination for $100 billion in data centre investment, according to reporting by Falice Chin, The Hub‘s Alberta bureau chief. A hyperscale data centre can consume more than 11 million litres of water per day, roughly half the daily use of a mid-sized city such as Airdrie, Chin noted. She also reported that the provincial grid operator, AESO, has capped near-term connections for large-load projects at roughly 1,200 megawatts after expected demand far outpaced supply, forcing developers outside that queue to bring their own generation. Chin argued rural communities are absorbing many of the risks of the boom while the economic rewards consolidate in cities such as Calgary and Edmonton.

Similar friction has surfaced elsewhere in Alberta. Rocky View County councillors rejected a local land-use plan for a smaller data centre after residents raised concerns about water supply and the loss of farmland, Chin reported. The provincial government, meanwhile, is rewriting its Water Act for the first time in 25 years to give regulators more flexibility over how water is shared and transferred as industrial demand grows.

The Hub’s mission is to create and curate news, analysis, and insights about a dynamic and better future for Canada in a… Read more

Alberta Technology Minister Nate Glubish faced significant backlash during a town hall meeting regarding AI data centres, particularly in light of Meta’s $13-billion project. Residents expressed distrust and concerns over resource management, citing a lack of communication from the government. Despite the minister’s assurances about safeguards for water and land, community resistance is growing as major projects advance. Critics question the economic benefits and job creation associated with these developments, highlighting the broader implications of AI on local economies and labor markets, as Alberta positions itself for substantial data centre investments.

The Meta project is valued at $13 billion.

The natural gas plant supporting the project costs $4.6 billion.

A hyperscale data centre can consume more than 11 million litres of water per day.