Federal case over Ontario nuclear plant's worst fish kill hits procedural snag

Canada November 26, 2026 05:02 AM
Federal case over Ontario nuclear plant's worst fish kill hits procedural snag

Federal case over Ontario nuclear plant's worst fish kill hits procedural snag

Bruce Power is due back in court Dec. 9 after the Crown withdrew original 2 charges

Crown prosecutors were forced to start over in their case against the operator of Canada's largest nuclear power plant after Fisheries and Oceans Canada (DFO) initially filed federal Fisheries Act charges in the wrong court over a massive 2025 fish kill.

Bruce Power was charged under Canada's Fisheries Act in October with unlawfully killing fish and violating the conditions of its federal fisheries authorization in connection with a massive fish kill at the plant in 2025.

The case came before a provincial offences court in Walkerton, Ont., on Tuesday, where Crown prosecutors withdrew the charges so they could be brought before the proper court.

The Walkerton court office told CBC News that the new charges are identical to those withdrawn on Tuesday. Bruce Power is now scheduled to appear in criminal court on Dec. 9.

The Public Prosecution Service of Canada, the federal agency responsible for prosecuting offences under federal law, told CBC News in an email Wednesday that DFO originally laid the charges as provincial offenses, calling it an "administrative issue."

The court determined they should proceed as criminal charges under the Fisheries Act.

DFO would not answer specific questions by email from CBC News on Wednesday about why or how the charges were filed to the wrong court, saying only that the "change does not affect the substance of the case."

Megan Adams, Bruce Power's director of corporate communications and marketing, declined to comment on the court mix-up, citing the ongoing legal proceedings.

A fish kill of unprecedented scale

Millions of gizzard shad were killed after they overwhelmed the plant's cooling water system in February 2025, forcing Bruce Power to shutdown one reactor and reduce power at another.

As many as 4.95 million gizzard shad died in the incident, with dead fish washing ashore in lakeside communities for days. At the plant, the fish had to be scooped out with a crane and hauled to a landfill.

Dead gizzard shad seen here on a beach on Lake Huron in the spring of 2025 were reported washing up in many localities along the coast. (Submitted by Saugeen Ojibway Nation)

Federal and provincial records obtained by CBC News also revealed the incident "challenged reactor safety" and raised concerns about the growing risks posed by climate change to nuclear power plant cooling systems.

It was the largest fish kill in the plant's history and prompted an investigation by Fisheries and Oceans Canada, culminating in the two federal charges.

Bruce Power has operated the sprawling nuclear generating facility on the shores of Lake Huron, about 200 kilometres northwest of Toronto, since 2001, when it took over operations from provincially owned Ontario Power Generation.

The eight-reactor facility, originally built by Ontario Hydro in the 1970s and '80s, supplies roughly 30 per cent of Ontario's electricity.